28 Apr 2022

2000kVA Emergency Generator Install

Due to a fault in the HV network of a food factory in Northern Ireland, JJ Loughran was asked to source and install a 2000kVA backup generator to get the factory up and running for the following day.

By 4.00 pm, a network fault on the 11kV/415v transformer was traced and confirmed. A backup generator and fuel storage were sourced and loaded for transport by 8:30 pm. The generator was onsite at the food factory by 12:30 am, and the factory was operational and running on the generator by 4:00 am, just in time for factory production to start at 06:00 am, and 150 staff were able to work.